Work began in July of this year and according to the agreed schedule the work completion deadline is 12 months. The planned dynamics of works are reached. Wo central pillars and one pillar on the coast have been built.
Also, space has been created for the construction of two span structures over the green areas, and walls have been removed on the ramp C. The road has been extended in the location of the mosque Baćić with the supporting walls.
Furthermore, ramp C and utility relocation are done. The installation of the pedestrian walkway is in the final phase, which will ensure the safety of people and fast flow of traffic on the city longitudinal.
The contracted priceis10.86million euros, andthe companies that have taken over the works are bhfirmEuro–Asphalt and ŽGP. This is the firstphase ofwork on theXIITransversal, which is an extension from theentity to DobrinjathroughRajlovactoVogošćaloop. In these works a route of 900 meters will be included.
(Source: Klix.ba)